Skip to content

Industries · Earthworks & land development

Built for earthworks,cubic metre by cubic metre.

Track zones, cells and plots from clearing to serviced — with the diesel, fill and plant behind every cubic metre.

Zones, cells & plots

See every plotat a glance.

An area site is laid out as zones, cells and plots; roads and drains run by chainage beside them. Daily logs move each plot through its stages, and the grid shows where the work really is.

  • Cells and plots generated from a naming pattern
  • Progress per plot, cell and zone — and per km of road
  • Completion as a likely range per zone

Alaro Park Zone B · Cell 3

24 plots

  • Cleared 6
  • Cut & fill 8
  • Compacted 5
  • Services 3
  • Serviced 2
Cell 3 completion
likely 5–26 Jan
Plots complete
2 of 24

Stages

From bushto serviced plot.

Each unit moves through stages you configure. These are the template’s defaults.

  1. S/1

    Clearing

    Setting out, clearing, grubbing and topsoil strip.

  2. S/2

    Cut & fill

    Bulk cut, imported fill, haul and placing by layer.

  3. S/3

    Compaction

    Layer by layer, with density tests logged.

  4. S/4

    Drains & roads

    Lined drains, culverts and road base — by chainage.

  5. S/5

    Serviced

    Plot pegged, levelled and handed over.

Materials

Diesel, fill and culverts,before they run short.

Norms per cubic metre turn the remaining quantities into material to complete. The site tank and the stockpile are stock on the ledger, so run-out is a range you can act on.

  • Diesel per m³ and per machine hour
  • Material to complete for each zone
  • Run-out and reorder-by against supplier lead time

Material to complete · Zone B

Material On hand To finish Runs out
Diesel (l) 9,500 ≈38,000 4–6 d
Laterite fill (m³) 2,100 ≈7,400 3–5 d
Culvert rings (no.) 36 ≈120 12–15 d

Run-out is a likely range at the 7-day weighted use

Plant on every zone

Know which machineis on which zone.

  • T/1

    Fuel per machine hour

    Every issue from the site tank is matched to the machine’s hours — and flagged when it burns outside its band.

  • T/2

    Hours worked, idle, broken down

    Daily logs record each excavator, dozer and tipper’s hours, pre-filled from yesterday’s plant.

  • T/3

    Challenges by zone

    Unsuitable material, groundwater and access problems are tagged by zone, so repeat issues are solved once.

Earthworks & land development template

What’s in the template.

Start from the template, then change what is different — with the same admin tools every customer gets.

  • Work items

    • Clearing-to-services work item library
    • Roads, drains and culverts by chainage
    • Planned quantities per zone and layer
  • Norms & units

    • Diesel, fill and cement norms per m³
    • m³, m², loads, tonnes and litres
    • Zone · cell · plot naming pattern
  • Daily log & lists

    • Earthworks daily-log layout
    • Plant hours worked, idle and broken down
    • Delay causes: rain, fuel, breakdown, setting out
  • Plant & maintenance

    • Excavators, dozers, graders, rollers, tippers
    • 250 h / 500 h plans, km plans for tippers
    • Fuel and meter logging per machine

Get started

Start with one zone, free for 15 days.

Start on the Earthworks & land development template in minutes, then add zones and invite your team. Or talk to sales for a guided setup.